The contracting authority must always ensure the public opening of bids (which takes place automatically in the e-JN system), except in cases where ZJN-3 defines an exception to the implementation of the public opening of bids.
In the case of two-phase procedures, the opening of applications is not public.
The opening of bids must not take place earlier than one hour after the deadline for submission of bids.